Longford CO2 Plant

Air Liquide | BOC Australia
  • 35,000Total workhours
  • 100%Local labour
  • Live Environments
  • Cranage & Rigging
  • Enviro Controls & Monitoring
  • Bulk Excavations
  • Detailed Excavations
  • Stakeholder Engagement
  • Materials Solution Management
  • Ground Improvement
  • Slope Stabilisation
  • Foundation Piles
  • Roads, Pavements & Kerbing
  • HVAC
  • Lighting
  • Backfilling & Compaction
  • Site Dewatering
  • Site Establishment
  • Stormwater & Drains
  • Trenching
  • Retention Systems
  • PFAS Remediation
  • Social Procurement
  • Industrial civil construction works programme, including the installation of inground services as well as site specific plant and structures
  • Construction of incoming valving within existing Exxon Mobil facility, including earthing
  • Contaminated soil remediation – PFAS
  • Management of installation and commissioning of HVAC system
  • Installation of two large petrochemical wastewater tanks, including stainless steel pipelines
  • Installation of workshop and admin building structures, including septic and potable water; fire systems and pumps; earthing and electrical reticulation systems
  • Weigh-bridge construction